Successful acceptance test for the Petrochemical complex in Kirishi, Russia
Friday, 12 March 2010 13:56

The factory acceptance test of the EPKS system designed for the Petro-chemical complex in Kirishi, Russia, has been successfully completed. It is anticipated that Syscont will be assigned the project extension which encompass the development of new technological units and further improvement of the existing system.  

Currently Syscont is working on the as-built project documentation which has to be handed in by mid-2010.

 